RAJUK approval and land use clearance

The approval process for construction permits in Dhaka City, as regulated by the Rajdhani Unnayan Kartripakkha (RAJUK), involves several steps. To start any building construction in the city, whether you are an individual landowner or a development company, you must secure legal permission through the RAJUK plan approval process. The process requires various drawings, submitted in compliance with the Dhaka Mahanagar Imarat Nirman Bidhimala 2008 (DMINB-2008).

The plan approval process has four stages: land use clearance, the construction permit, the occupancy certificate and, for large projects, special project permission.

Step 1: Land use clearance (LUC)

The first and essential part of the plan approval process is land use clearance. The application goes to the Town Planning Department at RAJUK on Form 101. The form must be filled out properly and signed by the landowner or an authorised representative.

Documents for the LUC application

  • Land registry copy
  • Via land registry copy
  • Duplicate carbon copy (DCR)
  • Mutation copy
  • Updated land tax copy
  • CS, RS and MS khatian
  • National ID or passport copy
  • One passport-size photo
  • Application fee as a bank draft in favour of RAJUK
  • LUC application (Form 101)

Additional documents for housing land

  • Possession letter copy
  • Payment clearance copy
  • Lease deed copy
  • Allotment letter
  • Sale permission, if applicable
  • Mutation permission
  • Layout plan from the housing office
  • Reconstruction permission, if applicable
  • Time extension, if applicable

Drawings for the LUC application

  • Digital land survey report, at 1:5000 or 1:10000
  • Location map of the land
  • RS and CS maps superimposed
  • Site plan showing land use within 250 m (15 cm × 20 cm)
  • Width of the nearest road

Information needed to fill in Form 101

  • Name of the applicant or landowner
  • Present address of the applicant or landowner
  • Proposed land use of the plot
  • Existing land use of the plot
  • Location of the land
  • Area of the land in katha
  • Ownership history of the plot
  • Name and width of the connecting road
  • Other land information, if any
  • Land use of the surrounding plots to the north, south, east and west
  • Level of the land relative to the road (reduced level)

Time for LUC approval

The official time for LUC approval is 30 days from the date the application is submitted. It can take longer due to unavoidable circumstances.

Fee for LUC approval

The application fee for land use clearance is Tk 1,000, plus 15% VAT. The fee is deposited as a bank draft in favour of RAJUK at a scheduled bank.

Validity of an approved LUC

An approved LUC is valid for 24 months from the date of approval. It can be renewed once for another 12 months by applying on Form 111. You should submit the construction permit application to RAJUK before the validity runs out. If it expires, you have to get land use clearance again.

Step 2: Construction permit (RAJUK plan approval)

Once land use clearance is approved, the next step is to submit the construction plan for a building permit. The plan is submitted on RAJUK’s Form 301, within the 24-month validity of the LUC. Here is the full process for getting RAJUK plan approval for building in Dhaka City.

Documents for the plan submission

  • Application form for the construction permit (Form 301)
  • Land use clearance copy
  • Bank draft copy of the building approval fee
  • All the land documents listed in the land use clearance section
  • Soil test report, if applicable
  • FAR calculation sheet, showing MGC, setbacks, number of storeys and so on
  • Ammonia-printed approval drawing sheets, in standard A0 to A4 sizes
  • Indemnity bond for piling or basement construction
  • Number of apartments on each floor
  • RAJUK registration and IAB membership certificate of the design architect
  • RAJUK enlistment and IEB membership certificate of the structural engineer
  • Land surrender deed for a proposed road extension

Qualifications of the design architect

To prepare and sign the RAJUK approval drawing sheet, the design architect must have:

  • A Bachelor of Architecture from an IAB-accredited university
  • Membership of the Institute of Architects Bangladesh (IAB)
  • At least 8 years of experience designing buildings of any type
  • Registration with RAJUK under DMINB-2008

Qualifications of the structural engineer

To carry out the structural analysis and design and sign the approval sheet, the structural engineer must have:

  • A BSc in civil engineering from an IEB-accredited university
  • Membership or fellowship of the Institution of Engineers, Bangladesh (IEB)
  • Registration with RAJUK as a structural design engineer under DMINB-2008
  • At least 8 years of experience in civil engineering, including 5 years in structural design

What the RAJUK approval sheet contains

  1. The title of the plan approval sheet.
  2. Name, address, mobile number and signature of the applicant.
  3. Name, address, mobile number, IAB membership number, RAJUK registration number and signature of the architect.
  4. Name, address, mobile number, IEB membership number, RAJUK enlistment number and signature of the structural engineer.
  5. LUC approval reference number and date.
  6. Occupancy type of the proposed building.
  7. CS, RS and SA dag numbers, mouza and thana of the proposed plot.
  8. Site plan at 1:4000.
  9. Layout plan at 1:200, showing:
    • The site boundary with measurements
    • Existing buildings, if any
    • The name and width of the connecting road
    • The main entry to the proposed building
    • The underground water reservoir, septic tank and soak well
    • The sanitary plumbing connection plan
    • The waste collection point
  10. Floor plans at 1:100, showing:
    • The position and dimensions of every room
    • The position and dimensions of doors and windows
    • The stair, lift, lobby and fire exit, if required, with measurements
    • The roof plan, with the terrace, chilekotha, lift machine room, overhead water tank and water disposal plan
    • The parking plan, with the entry, exit, guard post and driveway
    • The generator and substation rooms
  11. Two cross sections at 1:100, along the long and short directions, showing:
    • The height of every floor
    • The lift, overhead water tank and underground water reservoir
    • The lift machine room and parapet wall
    • The plinth level relative to the road and footpath
    • The existing and finished ground levels
  12. North, south, east and west elevations at 1:100.

Construction permit fees

The approval fee is deposited in favour of RAJUK at a designated bank, on this schedule:

Floor area Fee
Up to 50 sqm Tk 175
Over 50 to 100 sqm Tk 350
Over 100 to 200 sqm Tk 525
Over 200 to 300 sqm Tk 700
Over 300 to 500 sqm Tk 1,300
Over 500 to 1,000 sqm Tk 3,600
Over 1,000 to 1,500 sqm Tk 7,800
Over 1,500 to 2,000 sqm Tk 11,000
Over 2,000 to 3,000 sqm Tk 26,000
Over 3,000 to 4,000 sqm Tk 41,500
Over 4,000 to 5,000 sqm Tk 62,000
Over 5,000 to 10,000 sqm Tk 83,000
Over 10,000 to 15,000 sqm Tk 105,000
Over 15,000 to 20,000 sqm Tk 130,000
Over 20,000 to 30,000 sqm Tk 207,000
Over 30,000 sqm Tk 365,000

15% VAT is added to these fees.

Validity of the approved plan

An approved plan stays in force for 3 years from the date of approval. Within that time, construction must reach at least plinth level. If it does not, the approved plan becomes void.

Special conditions for plan approval

  • The land must be completely vacant before the plan is submitted.
  • The land must be surrendered for the proposed road widening, which means removing any existing boundary wall that stands in the way.
  • The minimum proposed road width is 20 feet for public land and 25 feet for housing land.
  • Where the dwellers share a road, the proposed road width can be reduced to 12 feet.
  • Near airports and runways, the height limits of the Civil Aviation Authority of Bangladesh (CAAB) apply, and height clearance must be obtained from CAAB through RAJUK.
  • The plot entry gate must be at least 18 feet wide, or the plan will not be approved.
  • The driveway must be at least 14 feet wide.
  • Buildings over six storeys must have a lift.
  • Buildings taller than 33 metres, or with more than 10 storeys, must have fire stairs.

Step 3: Occupancy certificate

When construction is complete, you must get an occupancy certificate from RAJUK before moving in. The certificate is valid for 5 years at first and must then be renewed every 5 years. If it is not renewed, the approved plan becomes invalid. Re-approving the plan then costs 10 times the plan approval fee, plus any compensation the Plan Approval Committee sets. To get the occupancy certificate you need:

  • A construction completion report
  • The as-built architectural design
  • The as-built structural design
  • The building services plan

Step 4: Permission for special or large projects

DMINB-2008 classifies some developments as special or large projects. These need separate special project permission from RAJUK’s Special Project Approval Committee, applied for on the Special Project Approval Form (Form 201). It is the last stage of RAJUK’s plan approval procedure for construction permits in Dhaka City. A project counts as a special project if it is:

  • A residential building with more than 40 apartments
  • Over 7,500 sqm of gross floor area, as counted for the floor area ratio (FAR)
  • A shopping mall with more than 5,000 sqm of floor area
  • Linked to a national or regional highway
  • A brickfield or a hazardous industrial factory
  • Within 250 metres of a historical building
  • Within 250 metres of a park or another area of natural beauty
  • Within 50 metres of hills or a riverbank

Documents for a special project application

  • A copy of the land use clearance or a no-objection certificate
  • Proof of ownership or a copy of the land registry
  • CS, RS and MS maps
  • Dag number, mouza and thana
  • Khatian, mutation records and so on
  • The number of storeys in the proposed building
  • The total floor area
  • The area of each floor and its use
  • The total number of flats
  • The floor area ratio (FAR) calculation chart
  • The water demand of the proposed project
  • The water source and supply network
  • The electricity demand of the proposed project
  • The electricity source and a supply diagram
  • The construction start date and phases
  • The expected time to complete construction

Drawings for special project approval

  • Site boundary measurements
  • A north sign on the proposed site
  • Name and width of the connecting roads
  • Holding number, plot number and mouza of the project
  • Plot level relative to the road
  • Existing buildings on the project site
  • Heights of neighbouring buildings and their distances from the plot boundary
  • Vehicle and pedestrian entry and exit points
  • The drainage system and disposal network
  • The location of the electrical substation
  • Wastewater and sewage treatment plants
  • Garbage collection and disposal
  • Any special buildings within 250 metres of the proposed land

Time for special project approval

The official time for special project approval is 45 days from the date the application is submitted, but it can take longer due to unforeseen circumstances.

Fee for special project approval

The special project approval fee is Tk 10,000, plus 15% VAT, deposited as a bank draft in favour of RAJUK.

Validity of an approved special project

An approved special project is valid for 24 months from the date of approval and cannot be renewed. If you do not apply for the construction permit within that time, you have to get special project approval again.

Conclusion

The RAJUK plan approval process for construction permits in Dhaka City can be long and complex. Many architecture firms in Dhaka can guide you through it, and choosing a reputable, professional firm speeds up the whole process. At Dhaka Designer, we have been working in this field for over 10 years and have completed about 100 projects.

More insights

Read all insights

Have land or a project in Dhaka?

Tell us about it. We will tell you the honest next step.

What do you need?

Choose one to get the right person’s phone and WhatsApp.

Choose what you need, and the phone number and WhatsApp of the person who handles it show here.

Md Tofael Mridha

Sales Manager

+880 1783-014360

Kazi Firoz Wadud Rafi

Director and Senior Architect · Archigram

+880 1676-942033

Abid Hussain

Managing Director · VizKit

+880 1717-619805

Kazi Faruk Wadud Rohan

Marketing Manager (DDBML)

+880 1917-042031

Arif Ashraf Image

Founder and Managing Director · Dhaka Designer

+880 1705-847906

Md Tofael Mridha

Sales Manager

+880 1783-014360

Or send us a message.

Fields marked * are required.